Aquarium Mains Upgrade

  • by

As part of ongoing upgrades, Limegreen Electrical were asked to change an ageing 400A automatic transfer panel and three associated distribution boards. Extensive planning and co-ordination, along with 125m of temporary powerlock & distribution, was required to maintain supplies to life critical systems for the wildlife and ensure the attraction could remain open. The project took 5 days to complete, with minimal disruption of the day to day operation.